[Project Name]: Jinzhu Group Curtain Wall Project
[Project Area]: 21,000 square meters
[Project Location]: Dongguan, Guangdong, China
[Start Time]: October 9, 2012
[Completion Time]: September 1, 2013
[Construction Duration]: 210 days
[Customer Requirements]: Standardized curtain wall construction, materials from first-line well-known brands, implemented according to the design effect
[Material Selection]: Stone Curtain Wall + Glass Curtain Wall
[Customer Evaluation]: We have two new industrial curtain wall projects, with relatively high requirements. We screened more and saw the determination and technology of Middle East Curtain Wall to do a good job of curtain wall. We have given us curtain wall solutions many times, which made us understand that the entire curtain wall project is relatively clear and clear. We firmly believe that cooperating with Middle East Curtain Wall will definitely be the kind of curtain wall building we want. As expected, we were not disappointed. Although the entire curtain wall project took a long time, the final effect was very satisfactory. We look forward to more cooperation opportunities in the future.
Summary
This customer has two curtain wall projects, one of which is 8,000 square meters and the other is nearly 13,000 square meters. The first building, 8,000 square meters, was almost completed before the exterior building curtain wall form was determined. Based on the characteristics of the building exterior wall and considering the practicality and aesthetics of the industrial park, we finally decided to use the stone curtain wall + glass curtain form. We made several plans for the customer, each of which used better decorative materials. In the end, the customer chose us to do it.